Scheduled
Projects
NDDOT-administered
Fargo construction projects through 2005
Revised Schedule (as of March 26, 2002)
2002
* Temporary repairs on damaged I-94 westbound bridge over I-29
* Reconstruction of southbound I-29 from Main Ave to 40th Ave S
* Reconstruction of 13th Ave S from 21st St to 40th St
* Reconstruction of 38th St from 4th Ave S to 17th Ave S
* Various types of work on 19th Ave N from Dakota Drive to I-29
* Construction of railroad shoo-fly (track detour) north
of Main Ave
2003
* Pavement repair projects on I-94 from near the Raymond interchange
to the Red River
* Reconstruction of Raymond interchange
* Reconstruction of Mapleton interchange
* Construction of new railroad bridge north of Main Ave
* Construction of I-94 noise walls from the 5th St underpass to
University Drive, both sides of I-94
* Reconstruction of Main Ave bridge over the Red River between Fargo
and Moorhead
2004
* Reconstruction of Main Ave from 25th St to 45th St
* Reconstruction of 12th Ave N from University to 25th St
2005
* Reconstruction of University Dr from 1st Ave N to 1st Ave S (joint
project with city of Fargo)
* South University Dr from 40th Ave S to 52nd Ave S
|