
Trucks dump rock from the construction bridge onto a
lumber mattress across the channel of the Missouri River during the closure of the
Garrison Dam. The dam was built between 1948 to 1953. Forum File Photo
The quest for water
By Patrick Springer
The Forum
The crusade to route water from the Missouri River to dry places in North Dakota found an
early champion in Edward Edson Heerman.
Low water levels in Devils Lake forced Capt. Heerman to dry-dock his steamboat, the Minnie
H., in 1909.
It was an undignified retirement for an old gal whose quarter-century of service began by
delivering military supplies to Fort Totten and ended as a ferry for summer chautauqua
festivals.
And so, when the movement to divert Missouri River water to the east took root in Devils
Lake in the 1920s, Heerman had the rudder from the old Minnie H. made into gavels and
presented as gifts to curry favor in Washington.
Those early efforts ultimately became, decades later, the Garrison Diversion Unit: 120
miles of canals, pumping stations and other public works that deliver water ... nowhere,
really, outside of a few wildlife areas.
Today, 30 years after construction began transforming the North Dakota prairie, the
project remains incomplete and mired in controversy.
Almost $600 million has been spent on Garrison Diversion and related projects; it's been
authorized three times by Congress, and demonized countless times by economists and
environmentalists.

Workers undertake the task of completing
construction of one of the eight upstream portals in the Garrison Dam's intake area. Forum
File Photo
After decades of bickering and negotiating with neighbors in Canada and
Minnesota, Garrison Diversion is left with two formidable obstacles: The 22-mile gap of
prairie between its two completed stretches of canals - and the estimated $800 million it
would cost to finish the job.
And surmounting those challenges assumes the project could overcome environmental concerns
from Canadian officials, who remain unconvinced that water from the Missouri could be
treated to prevent transfer of foreign fish species and diseases to the Hudson Bay, via
the Red River.
Plans for Garrison Diversion have changed dramatically over the years, altered because of
objections about the economic unfeasibility and environmental damage of early proposals.
Schemes to divert Missouri River water originally were driven by desires to irrigate huge
tracts of semiarid prairie.
Before Garrison, in 1942, plans called for irrigating 1 million acres in northwest North
Dakota with water supplied by Fort Peck Dam in Montana. That evolved into a
Missouri-Souris diversion to irrigate 1.1 million acres in the Crosby-Mohall region, but
was scrapped in 1947 because most of the soil was unfit for irrigation.
By the time Garrison Diversion was authorized in 1965, however, the number of irrigation
acres had shrunk to 250,000. And today, the proposal circulating in Washington calls for
only 78,000 acres of irrigation.
The impetus for the metamorphosed Garrison Diversion is to deliver water for municipal,
residential and industrial use in eastern North Dakota, principally to stabilize Devils
Lake and to assure water for growth in the Red River Valley.
"There's going to be a revival of interest in irrigation, I'm sure," says Russ
Dushinske of Devils Lake, a former board member of the Garrison Conservancy District.
Dushinske was in high school when his family moved to Devils Lake in 1930. He saw the
lake's level drop dramatically in just one year at Creel Bay. "In 1930 we could swim
in the bay and 1931 we couldn't swim anymore. It was that bad."
As a young reporter for the Devils Lake Journal, Dushinske met Sivert Thompson, a local
lawyer who galvanized support for diverting Missouri River water to the east; Thompson, in
turn, had been a contemporary of Edward Edson Heerman in the quest to deliver water.
Garrison's early nemesis was its staggering price tag: estimated at $529 million in 1957,
when grandiose plans envisioned 6,773 miles of main and lateral canals - more miles than
the state's highway system at the time - and eight reservoirs, 656 pumping stations to
supply water to 41 towns.
Time was not on Garrison's side; it had to wait in line while other massive water projects
in the West were built first. "Unfortunately, we tended to be at the tail end of the
reclamation projects," says C. Emerson Murray, who served as manager of the Garrison
Conservancy District from 1985 to 1994, and whose involvement in the project began in the
1950s.
The cost of completing Garrison Light, as it currently is proposed, is $1.6 billion,
including past and projected future spending.
Beginning in the late 1960s, the project encountered another adversary: a burgeoning
environmental awareness and activism.
Environmental opposition to Garrison is embodied more than anyone else, in a veterinarian
whose specialty is waterfowl diseases named Gary Pearson.
Pearson came to Jamestown, N.D., in 1967 to work for the U.S. Fish and Wildlife Service's
Northern Prairie Center. The news at the time was full of talk of the economic promise of
the mammoth Garrison project. But Pearson found that many of his fellow wildlife
specialists and biologists were skeptics.
In 1974 Pearson served as editor of an environmental impact statement of Garrison by the
Institute of Ecology, an experience that convinced him the plan would improve neither
water quality nor economic vitality.
"There was nothing about the project that was good," says Pearson, whose
outspoken opposition to Garrison ultimately cost his job with the Fish and Wildlife
Service.
A pivotal moment in the fate of Garrison Diversion came in 1977, when the International
Joint Commission recommended against building any features that would transfer water - and
biological organisms - from the Missouri Basin to the Hudson Bay, a devastating
development.
"Unbelievable and aghast," Murray says, recalling his reaction. "The United
States - well, I might as well say it - had awfully poor representation on the joint
commission. It had become a place for hacks."
Pearson, still an active Garrison gadfly, believes state officials erred by not
acknowledging earlier the project's drawbacks and switching to smaller-scale projects, as
South Dakota did in 1977, when it backed away from the Oahe irrigation project and pushed
alternatives.
"They're getting on with water development down there," he says. "We're
still fighting over it."
A better solution for delivering water to the Red River Valley, Pearson believes, would be
to build a pipeline beginning at Lake Sakakawea on the Missouri and ending at a water
treatment plant serving Fargo. He says the cost of a pipeline once was had a preliminary
"ballpark" estimate of $400 to $500 million.

The Snake Creek Pumping Plant stands at
the Garrison Dam deck elevation of 1,867 feet. Forum File Photo
Although completion of the project still remains an elusive goal, backers still point to
notable accomplishments.
Since the project was reformulated in 1986, $335 million has been spent, including $160
million for municipal, rural and industrial water supply, much of which went to the
Southwest pipeline to serve Dickinson, N.D., and surrounding communities.
- Continued -
|
Key dates in
regional water issues
The Forum
1889: The North Dakota Constitutional Convention
considers a plan to build a canal from the Missouri River in Montana to divert water to
the Red River for irrigation.
1924: Sivert Thompson and others in Devils Lake, N.D., form the Missouri
River Diversion Association to promote schemes to raise the lake level and supply eastern
North Dakota with water.
1927: The engineering dean at the University of North Dakota proposes
diverting water from the Missouri into Devils Lake and the Sheyenne and James rivers via a
30-mile canal.
1935: The Army Corps of Engineers is considering building a great earth
dam across the Missouri River near Garrison, N.D.
1944: Congress passes the Pick-Sloan plan, a massive program to build
five dams on the Missouri River, including Garrison Dam. Plans later call for 1 million
acres of irrigation in northwest North Dakota, authorized as the Missouri-Souris Unit.

Lights illuminate the Garrison Dam construction site. Forum File Photo
1947: Giant earth-moving machines begin forming the embankment of Garrison Dam.
Over the years, more than 2,300 men worked on the project, sometimes working
round-the-clock shifts.
1953: President Eisenhower dedicates Garrison Dam in a closure ceremony.
Reservoirs from Garrison and Oahe Dam in South Dakota flood 465,000 acres of river bottom
land in North Dakota.
1965: Congress authorizes the Garrison Diversion Unit to irrigate 250,000
acres and divert water to stabilize Devils Lake - low throughout most of its
post-settlement history - and the Red River Valley. The project's estimated cost is $212
million. Earlier authorization attempts in 1960, 1963 and 1964 failed.
1969: Construction begins on the Snake Creek pumping plant to lift
Missouri River water from Lake Sakakawea into McClusky Canal, designed to carry water to
central and eastern North Dakota. Construction on the pumping station ends in 1976 at a
cost of $19.2 million. McClusky Canal is built from 1969 to 1976; it stretches 74 miles,
beginning on the east shore of Lake Audubon and ending near the Sheyenne River.
1972: The Committee to Save North Dakota, an organization of landowners
along the McClusky Canal route, files suit to require an environmental impact statements
for the project.
1973: The government of Canada files a formal request asking for a
moratorium on Garrison Diversion construction until concerns can be addressed. The
Canadians worry that small foreign organisms could enter the Hudson Bay from the Missouri
Basin.
1976: The National Audubon Society sues the government, alleging that the
final environmental impact statement for Garrison is flawed. An agreement is reached for a
new environmental impact assessment to consider other alternatives.
1977: The Carter administration announces it is cutting funding for
Garrison, one of 19 water projects slated for termination. After protests from western
governors, the administration relents, but recommends Garrison's irrigation capacity be
reduced to 96,000 acres from 250,000 acres.
1977: The International Joint Commission concludes that, even with the
best engineering talent and operating procedures, Garrison Diversion ultimately would
transfer marine organisms from the Missouri River Basin to the Hudson Bay, via the Red
River. It recommends that the parts of the project that could affect waters flowing into
Canada - 87 percent of the 250,000 irrigation acres - not be built.
1983: Construction begins on the New Rockford Canal, which extends 44
miles and is intended as the main point of water delivery to eastern North Dakota and the
Red River Valley. Construction is completed in 1991.
1984: Serious questions confront Garrison over environmental concerns,
land acquisition and the economics of irrigation. Construction on Garrison Diversion is
halted, and a high-level commission is appointed to study changes.
1984: The Garrison Diversion Unit Commission recommends major changes in
the project, including eliminating the planned Lone Tree Reservoir, which would mean a
huge decrease in irrigation capacity. The cost of completing the project is estimated at
$1.12 billion.
1986: In a compromise to satisfy environmental critics in the United
States and Canada, Congress re-authorizes Garrison, reducing irrigation to 130,000 acres.
The new plan emphasizes municipal, rural and industrial water supply, and provides for a
$12 million wetlands trust.
1986: A government panel concludes that the original $12.6 million
settlement for 153,000 acres paid the Three Affiliated Tribes for 153,000 acres flooded by
the Garrison reservoir is grossly inadequate. The panel recommends additional compensation
ranging from $178.4 million to $342.9 million.
1990: The Bush administration recommends ending funding for Garrison
Diversion in the 1991 budget. An inspector general's report concludes that few, if any,
municipal, rural and industrial systems would receive water from Garrison because their
locations were impractical or too costly. The report also finds that farmers wouldn't be
able to afford their share of irrigation costs.
1991: With Garrison's future in jeopardy, a task force meets to explore
strategies for water development in North Dakota. The task force recommends increasing
state sales and income taxes to raise $22 million for water projects. The Legislature
rejects the water tax package.
1992: In a vote widely seen as a statewide referendum on Garrison
Diversion, voters spurn an initiated quarter-cent sales tax for water projects.
1995: The North Dakota Legislature repeals part of a law protecting
wetlands. The National Wildlife Federation interprets the move as withdrawal of state
support from a collaborative process to reach compromise on Garrison Diversion, and
withdraws its cooperation.
1998: The North Dakota congressional delegation introduces the Dakota
Water Resources Act, the latest version of Garrison Diversion, calling for 70,000
irrigation acres and seeking $200 million to help complete facilities to deliver water to
the Red River Valley, $200 million for water projects on Indian reservations, $300 million
for other water projects, $25 million for a natural resources trust and $40 million to
demolish and rebuild the Four Bears Bridge at New Town, N.D.
1998: The Canadian ambassador writes to a Senate subcommittee chairman to
make clear that Canada remains opposed to diverting water to the Hudson Bay. The
ambassador says diversion poses an "unacceptable risk of irreversible damage to
Canadian waters from the potential transfer" of non-native fish species and diseases.
A Minnesota official testifies about the state's "consistent opposition" to
Garrison Diversion.
- Continued -
|